Chesapeake Announces Proprietary Heap Oxidation Technology Updates

Chesapeake Gold reports that tests of its heap oxidation process at Metates, Durango, achieved 70% gold and 61% silver recovery from the main intrusive domain in 90 days, versus 240 days in earlier testing. It is evaluating further improvements for a planned prefeasibility study and testing the process on six third-party projects.

Mammoth Provides Update On Field Activities at its Tenoriba Gold-Silver Property, Mexico

Mammoth Resources has collected a 200 kg metallurgical sample from the Carneritos area of its Tenoriba gold-silver project in Chihuahua. The sample will undergo vat and column leach testing at the Universidad de Sonora to assess recovery options for potential small-scale production. The company also reviewed drill core, site access and plans to renew surface access agreements.

GoGold Advances Los Ricos South Construction

GoGold reports that construction at Los Ricos South in Jalisco remains on schedule for first silver production in the second quarter of 2028. More than 150 contractors are on site, plant design is 90% complete, and all long lead equipment has been ordered. The company says the project is fully funded.

Endeavour Silver Reports Temporary Reduced Capacity at its Guanacevi Mine

Endeavour Silver has taken the primary ball mill at its Guanaceví mine offline for repairs expected to take about three weeks. During that period, processing capacity will fall from approximately 1,100 to 600 tonnes per day. Mining will continue uninterrupted, and replacement parts are already on site.

ANT Commences Trading as Tecomatlán Advances Toward Commissioning

Antimony Resources commenced ASX trading under ticker ANT following its name change from EV Resources. At the Tecomatlán antimony processing plant in Mexico, crushing for the proof-of-concept campaign is underway, with material being stockpiled ahead of grinding and flotation as the company advances toward full commissioning.

Apollo Silver Clarifies Media Reports Regarding Ejido Benito Juárez Assembly

Apollo Silver disputes reports that Ejido Benito Juárez voted to reaffirm its 2012 mining moratorium. The company says the September 20 assembly was adjourned for lack of quorum, leaving the proposed lifting of the moratorium and access agreement for its Cinco de Mayo project undecided. Apollo expects the ejido to reconvene, likely in October.