Arian Silvers Chief Executive Officer, Jim Williams, commented today, The phased commissioning of the Companys processing plant has been ongoing during the second quarter of the year.The commissioning process has highlighted the need for remedial work to the tertiary crusher which will result in a delay in completion of commissioning into Q4 this year, and a corresponding delay in mine development. The silver price has continued to fall this year, recently touching a six year low and current market consensus is for continued short-term weakness. Therefore, it has become clear that alterations to the mine plan will be required if profitable production is to be achieved in the current climate…”