Fortuna provides update on the resumption of construction activities at the Lindero gold Project, Argentina
Open pit mining is planned to gradually resume in July 2020. During the period from July to December 2020, an estimated 1.7 million to 1.9 million tonnes of ore are scheduled to be placed on the leach pad with an average gold grade of 1.00 g/t to 1.10 g/t. The estimated stripping ratio during this period is 0.68 to 0.75.