Torex Announces Arrangements To End The Illegal Blockade Of Its El Limon-Guajes Mine
Torex Gold Resources Inc. is pleased to announce that arrangements have been made to lift the illegal blockade of its El Limon-Guajes Mine at 6 PM on Thursday April 14th. Between now and then, operations and contractor personnel will be mobilized to site and the operations will be re-started on night shift of April 14th. During the temporary stoppage a number of maintenance, fine tuning, and commissioning activities were completed. These included the replacement of the SAG mill liners, chute adjustments, piping improvements, filter cloth replacement and the final commissioning of the RopeCon. In addition, resettlement activities at the new village of Real del Limon were completed with all of the families now moved into their new homes.