Vizsla Silver Provides Update on Panuco Project Development
Vizsla says Panuco is nearing construction readiness, with engineering 50% complete, 85% of planned plant equipment ordered and three development contracts awarded. It is coordinating with Mexican authorities on security before a phased site return. First silver is now targeted for H2 2028, delayed one year; no production decision has been made. Vizsla also pledged US$5 million to a community foundation.