Silverco Provides La Negra Update: First New Underground Equipment Onsite and Tailings Filtration Project Advanced
Silverco’s first new Epiroc development jumbo is being commissioned underground at La Negra, Querétaro, with more loaders due by December and a Simba S70 drill in Q1 2027. M3 will manage the tailings filtration plant, with civil works starting late November and completion by end H1 2027, when the mill should return to 2,500 tpd.