Sierra Madre Announces Guitarra Processing Plant Achieves Throughputs of up to 720 Tonnes per Day as Development at Nazareno and Guitarra Mines Accelerates
Phase 1 modifications lifted Guitarra plant throughput to 720 tonnes per day, over 40% above its previous 500-tpd capacity. Sierra Madre reported the new ball mill installed and expected commissioning in November, supporting a Phase 2 target of 1,200–1,500 tpd. Mine development reached 2.6 km since June, and groundwork began for the tailings facility expansion.