First Majestic Files NI 43-101 Technical Report for the Los Gatos Silver Mine

First Majestic filed an NI 43-101 Technical Report for the Los Gatos Silver Mine in Chihuahua, supporting Mineral Resource and Reserve estimates effective December 31, 2025. The report contains no material changes from estimates disclosed in March. First Majestic owns 70% of Los Gatos and operates the mine, with Dowa Metals & Mining holding 30%.

GoGold Commences Construction of the Fully-Funded Los Ricos South Mine

GoGold Resources commenced construction of the fully funded Los Ricos South Mine in Jalisco following receipt of its federal permit in June. The company has US$284 million cash and zero debt. Plant design is 85% complete, earthworks are underway, and underground development begins January 2027. First silver-gold production is targeted for June 2028.