Endeavour Silver Provides Terronera Progress Update

Endeavour Silver said the Terronera project faced delays in structural steel deliveries, slowing lower-platform and filter area work and pushing wet commissioning to early Q2 2025. The company temporarily reduced its workforce over the holidays to cut costs. Critical steel deliveries have resumed, dry commissioning continues, ore stockpiles are nearly full, and grinding-mill tests are underway.